Telegraph Road, Beltway Closures This Week

The latest closures from the Woodrow Wilson Bridge Project.

 

Looking for the latest information on traffic conditions and local gas prices? Go to the traffic and gas section at rosehill.patch.com/traffic.

Weather permitting, the Woodrow Wilson Bridge Project will be conducting Telegraph Road interchange and other area closures January 27-February 3.  Variable message signs will be posted to alert drivers and provide detour information when necessary.  This work will have significant impacts on Beltway and local traffic, and motorists are strongly advised to seek alternate routes to avoid delays. The scheduled work is as follows.

Find out what's happening in Kingstowne-Rose Hillwith free, real-time updates from Patch.

TELEGRAPH ROAD INTERCHANGE CLOSURES

Monday, Jan. 30 OVERNIGHT from 9 p.m. to 5 a.m. the next day; also Monday, Jan. 30 through Thursday, Feb. 2 DAILY from 9 a.m. to 3 p.m., and Friday, Feb. 3 from 9 a.m. to noon:

Find out what's happening in Kingstowne-Rose Hillwith free, real-time updates from Patch.

The ramp from Telegraph Road South to N. Kings Highway will be closed for roadway construction. 

  • o Detour:  Motorists should take the Huntington Avenue ramp to Huntington Avenue East to U.S. Route 1 South to N. Kings Highway. Note that the Monday overnight work rain dates are either Wednesday, Feb.1 or Thursday, Feb. 2.

Monday, Jan. 30 OVERNIGHT from 9 p.m. to 5 a.m. the next day; also Monday, Jan. 30 through Thursday, Feb. 2 DAILY from 9 a.m. to 3 p.m., and Friday, Feb. 3 from 9 a.m. to noon:

The ramp from Telegraph Road South to the Capital Beltway Outer Loop (I-95/495 North) will be closed for roadway construction. 

  • o Detour:  Motorists should take the Huntington Avenue ramp to Huntington Avenue East to U.S. Route 1 North to the on-ramp to the Outer Loop. Note that the Monday overnight work rain dates are either Wednesday, Feb.1 or Thursday, Feb. 2.

Monday, Jan. 30 OVERNIGHT at 11:59 p.m.:

Telegraph Road South will be completely closed for 15 minutes just after midnight from just before the ramp to the Capital Beltway Outer Loop (I-95/495 North) to Huntington Avenue for roadway construction.  The exit for the Outer Loop will be closed but the exit for the Inner Loop (I-95/495 South) will remain open.  Note that the rain dates for this work are either Wednesday, Feb.1 or Thursday, Feb. 2.

CAPITAL BELTWAY CLOSURES

Wednesday, Feb. 1 from 9 a.m. to 3 p.m.:

The right shoulder of the Capital Beltway Inner Loop (I-95/495 South) between Telegraph Road and the Eisenhower Connector will be closed to install signs.  All lanes of traffic in this area of the Inner Loop will remain open; only the shoulder will be closed.

MILL ROAD CLOSURES

Friday, Jan. 27 continuously until Friday, Feb. 3 at 3 p.m.:

  • One lane of Mill Road North where it connects to Telegraph Road South will be closed to complete the installation of safety features including guardrails, barriers and curbs.  One northbound lane will remain open.

Please use caution when traveling in this area. All construction-related work and dates are subject to change, depending on weather, material and contractor availability or other unforeseen conditions.